PACE A Partnership for an Advanced Computing Environment

June 12, 2019

Scheduled UPS Fan Replacement in Rich Data Center

Filed under: Uncategorized — Semir Sarajlic @ 8:44 pm

[June 12, 2019 – 4:45pm] OIT operations team notified PACE of a planned maintenance on Saturday, June 15, from 7:00AM – 2:00PM to replace a fan in one  of the UPS units in Rich Data Center.  This work may require that particular UPS to run in maintenance bypass and therefore that room would temporarily be without power backup.  No outage is expected from this work; however, in the case of an outage, PACE clusters and jobs running on them are at the risk of being interrupted.  Again, it is unlikely that we will have a power outage during this maintenance period.

For further details about this planned OIT maintenance, please visit the following  OIT link .

If you have any questions, please don’t hesitate to contact us at pace-support@oit.gatech.edu.

Powered by WordPress